Role-wise Workflow
The full 12-step Lead-to-Handover process, organized by department so each team can see exactly what they own and where they hand off — as clarified by the client on 25 Sep 2026.
Marketing1 step(s) owned
- Step 1. Lead Creation — A lead enters the system from any of several sources (website, referral, walk-in, exhibition, etc.).Pre-Sales
Sales3 step(s) owned
- Step 2. Initial Contact & Rough Estimate — Team connects with the customer, asks for details, and gives a rough estimate on call.Pre-Sales
- Step 3. Measurement Booking, Advance Payment & Sales Operator — If the customer requires measurement, they pay an advance payment, the lead is processed for measurement, and a Sales Operator is assigned.Pre-Sales
- Step 6. Work Order & Payment Terms — Work Order is generated with payment terms. Default split is Advance 50% / Dispatch 30% / Progress 10% / Handover 10%. Any change to these terms requires Management approval.Work Order & Delivery
Also collaborates on: Step 1 (Lead Creation).
Supervisor📱 Mobile App7 step(s) owned
- Step 4. Product, Design & Sample Selection — Supervisor selects the product code, uploads JPEG/DWG design files, and uploads approved sample photographs (front & back) — typically up to ~10 samples per project.Design & Sample Approval
- Step 5. Measurement Sheet & Final Quotation — Supervisor uploads the measurement sheet taken on site and updates the final quotation based on the confirmed measurements.Design & Sample Approval
- Step 8. Material Delivery & Delivery Challan — A Delivery Challan is created for the materials and quantities delivered to site.Work Order & Delivery
- Step 9. Daily Site Readiness Checklist — Supervisor checks site readiness daily, submits a checklist with photos and remarks, and selects the approximate start date.Site Execution
- Step 10. Contractor Allocation — On start, multiple contractors are assigned based on the different material tasks (e.g. Stone Cladding, Texture, Painting), with labour count, tentative finish date and remarks per contractor.Site Execution
- Step 11. Daily Supervision Report (DSR) — A DSR is submitted per contractor assigned, capturing site, contractor name, number of labour, current status photos, number of days to complete, and remarks.Site Execution
- Step 12. Final Measurement, Add-ons & Credit Note — After work completion, final measurement is updated and any add-on work is recorded. If the completed work amount is less than the amount already received, a Credit Note is created for the difference.Final Measurement & Closure
Accounts4 step(s) owned
- Step 6. Work Order & Payment Terms — Work Order is generated with payment terms. Default split is Advance 50% / Dispatch 30% / Progress 10% / Handover 10%. Any change to these terms requires Management approval.Work Order & Delivery
- Step 7. Order Placed — Accounts confirms the order is placed once payment terms are accepted.Work Order & Delivery
- Step 8. Material Delivery & Delivery Challan — A Delivery Challan is created for the materials and quantities delivered to site.Work Order & Delivery
- Step 12. Final Measurement, Add-ons & Credit Note — After work completion, final measurement is updated and any add-on work is recorded. If the completed work amount is less than the amount already received, a Credit Note is created for the difference.Final Measurement & Closure
Design0 step(s) owned
No steps directly owned — supports other teams only.
Also collaborates on: Step 4 (Product, Design & Sample Selection).
Manager1 step(s) owned
- Step 10. Contractor Allocation — On start, multiple contractors are assigned based on the different material tasks (e.g. Stone Cladding, Texture, Painting), with labour count, tentative finish date and remarks per contractor.Site Execution
Also collaborates on: Steps 6, 12 (Work Order & Payment Terms; Final Measurement, Add-ons & Credit Note).
Full Process — Step by Step (1 → 12)
| # | Step | Group | Primary Role | Collaborators | Description |
|---|---|---|---|---|---|
| 1 | Lead Creation | Pre-Sales | Marketing | Sales | A lead enters the system from any of several sources (website, referral, walk-in, exhibition, etc.). |
| 2 | Initial Contact & Rough Estimate | Pre-Sales | Sales | — | Team connects with the customer, asks for details, and gives a rough estimate on call. |
| 3 | Measurement Booking, Advance Payment & Sales Operator | Pre-Sales | Sales | — | If the customer requires measurement, they pay an advance payment, the lead is processed for measurement, and a Sales Operator is assigned. |
| 4 | Product, Design & Sample Selection | Design & Sample Approval | Supervisor | Design | Supervisor selects the product code, uploads JPEG/DWG design files, and uploads approved sample photographs (front & back) — typically up to ~10 samples per project. |
| 5 | Measurement Sheet & Final Quotation | Design & Sample Approval | Supervisor | — | Supervisor uploads the measurement sheet taken on site and updates the final quotation based on the confirmed measurements. |
| 6 | Work Order & Payment Terms | Work Order & Delivery | Sales / Accounts | Manager | Work Order is generated with payment terms. Default split is Advance 50% / Dispatch 30% / Progress 10% / Handover 10%. Any change to these terms requires Management approval. |
| 7 | Order Placed | Work Order & Delivery | Accounts | — | Accounts confirms the order is placed once payment terms are accepted. |
| 8 | Material Delivery & Delivery Challan | Work Order & Delivery | Supervisor / Accounts | — | A Delivery Challan is created for the materials and quantities delivered to site. |
| 9 | Daily Site Readiness Checklist | Site Execution | Supervisor | — | Supervisor checks site readiness daily, submits a checklist with photos and remarks, and selects the approximate start date. |
| 10 | Contractor Allocation | Site Execution | Supervisor / Manager | — | On start, multiple contractors are assigned based on the different material tasks (e.g. Stone Cladding, Texture, Painting), with labour count, tentative finish date and remarks per contractor. |
| 11 | Daily Supervision Report (DSR) | Site Execution | Supervisor | — | A DSR is submitted per contractor assigned, capturing site, contractor name, number of labour, current status photos, number of days to complete, and remarks. |
| 12 | Final Measurement, Add-ons & Credit Note | Final Measurement & Closure | Supervisor / Accounts | Manager | After work completion, final measurement is updated and any add-on work is recorded. If the completed work amount is less than the amount already received, a Credit Note is created for the difference. |